The Port of Tarragona begins to install the Balears wharf bollards

The Port of Tarragona begins to install the Balears wharf bollards
13 Jul
2021

This is the first of the 33 bollards to be installed with a pull capacity of up to 200 tons

These bollards are suitable for the world’s largest cruise liners

The Port of Tarragona has begun work on installing the bollards on the Balears Wharf. A total of 33 bollards with a capacity of 200 tons each will be installed to provide mooring for the world’s largest cruise liners.

The fenders, which are also being installed at a similar pace, and the bollards are the elements that take the strain of docking and tying up the vessel. Thus, when a ship is slowly approaching in a berthing manoeuvre, the fenders absorb the momentum of the vessel as it manoeuvres, protecting both the dock and the vessel when they come into contact. In conditions of strong winds and waves, the fenders and bollards are responsible for absorbing the vessel's energy, especially when it tends to approach or move away from the dock.

In parallel with the bollard installation, the Port is completing the final metres of the edge beam. The last section has already been concreted with a formwork trolley and only a few sections remain to be finished. This will be done manually due to the difficulty of access.

Facing the final stretch

The Port of Tarragona has begun to prepare the esplanade with the final earthworks ready for future paving. The first lampposts for lighting the dock are also being installed.

When the new infrastructure is in operation it will increase the capacity to receive more visitors and in better conditions. It will have a total berthing line of 700 metres, given that on 240 of the 460 metres it will be possible to tie up on both sides and the area of the Llevant breakwater has also been added. All this means that double the number of cruise ships can dock simultaneously and that the world’s largest cruise liners can be accommodated.

Most Visited

Work with us

Work with us

Job board of the Port Authority of Tarragona
Open Data

Open Data

Here you will find public data of the public character of the organization
Contractor Profile

Contractor Profile

Here you will find public data of the public character of the organization
Communication and press

Communication and press

News of interest and current affairs of the Port Authority of Tarragona
SEA

SEA

AGRI-FOOD DELIVERY SYSTEM
Ship location

Ship location

Gisweb, ship situation program, stopovers and movements
Requests for services via ports

Requests for services via ports

Requests for services and communications for the ship, the goods and the passage
Accreditation center

Accreditation center

Administrative process involved in certifying a company/organization to access the Port
Traffic

Traffic

Goods traffic at the Port Authority of Tarragona

 

SETMANES DE L'AIGUA | PORT TARRAGONA | De l'11 d'abril al 5 de maig

 ACTE CENTRAL 25 I 26 D'ABRIL - INSCRIPCIONS

 

 Acte central - 25 i 26 abril. Jornades Tècniques | La Gestió de l'aigua en un escenari de crisi climàtica. L’objectiu de les Jornades tècniques és abordar amb els actors implicats la complexitat de la gestió de l’aigua des d’una visió transversal: climàtica, ambiental, social i de governança. Més enllà de la sequera actual i de les incògnites que planteja, cal avançar cap a una gestió sostenible dels recursos hídrics.

Inscripcions 25 i 26 abril

25 i 26 abril

Registra't ara
+ info

L'AIGUA DEL FUTUR DE L'11 D'ABRIL AL 5 DE MAIG.És un esdeveniment compost de diverses jornades tècniques, debats, exposicions i art al Port de Tarragona que tindrà lloc durant els dies compresos entre l'11 d'abril i el 5 de maig en diversos punts del Port de Tarragona. Amb l'objectiu d'informar-vos sobre tota la programació i que no us perdeu res, us deixem totes les activitats a continuació:

 

Pàgina oficial de les Setmanes de l'Aigua Port Tarragona- Agenda i programació - accés lliure

 

Pàgina oficial Primera edició

Més informació PROGRAMACIÓ 
+ info

 

Mitjans col·laboradors