The southern breakwater now connected to the caissons of the future Port of Tarragona Balears Wharf

The southern breakwater now connected to the caissons of the future Port of Tarragona Balears Wharf
12 Nov
2020

This first connection allows the already-installed caissons to be reached by land

The first connection between the southern breakwater and the caissons of the Port Tarragona’s new Balears Wharf allows terrestrial resources to reach the caissons that have already been installed. This development, together with the construction of the northern breakwater, will enclose the Balears Wharf on both sides, giving it a highly recognisable shape.

This first land access to the caissons allows the 11 foundations to be filled with concrete by lorry, at the same time as the extrados with large-rock landfill is being built on the rear. In parallel to the construction of the southern and northern breakwaters, the dredger Ardenza is undertaking the auxiliary task of filling the 11 installed caissons from the sea. This process will complete the task of giving the necessary weight and consistency to the caissons ‒ the wharf’s foundations ‒ for any interventions that may be made in the future.

The construction of the two breakwaters is now being carried out exclusively by terrestrial resources. This phase uses diverse pieces of heavy machinery, including back hoes and the transportation by road of material from the El Llorito (Tarragona) and Blanco (Reus) quarries. The second mound situated to the north will also shortly be connected to the caissons, thus outlining the perimeter of the Balears Wharf.

Balears, a sustainable wharf

This new infrastructure will increase the Port’s capacity to receive more visitors in improved conditions. It will have a total mooring line of 700 metres, given that on 240 metres of its 460-metre length it will be possible to dock on both sides, as well as alongside the Llevant breakwater. All this will double the number of cruise ships that can dock simultaneously, as well as allowing the largest cruise liners in the world to tie up.

Moreover, the Port of Tarragona has designed this facility as a multipurpose wharf that will be able to handle different types of port traffic now and in the future. Currently, its priority use will be for passenger cruise liners and it is hoped this will be in operation in the middle of next year. The new infrastructure will have a very long operating life and its design ‒ in case it is needed ‒ will allow it to be converted to be used for solid bulks or other types of cargo.

The Port of Tarragona is studying the use of electricity connections to supply power to the different vessel auxiliary facilities while they are moored on the Balears Wharf. This will allow the use of internal combustion engines to be avoided, thus reducing pollution and saving fuel while the ships are docked in Tarragona. It is an infrastructure designed to adapt to the future challenges the Port of Tarragona is proposing with a view to making the Balears Wharf a sustainable wharf.

Most Visited

Work with us

Work with us

Job board of the Port Authority of Tarragona
Open Data

Open Data

Here you will find public data of the public character of the organization
Contractor Profile

Contractor Profile

Here you will find public data of the public character of the organization
Communication and press

Communication and press

News of interest and current affairs of the Port Authority of Tarragona
SEA

SEA

AGRI-FOOD DELIVERY SYSTEM
Ship location

Ship location

Gisweb, ship situation program, stopovers and movements
Requests for services via ports

Requests for services via ports

Requests for services and communications for the ship, the goods and the passage
Accreditation center

Accreditation center

Administrative process involved in certifying a company/organization to access the Port
Traffic

Traffic

Goods traffic at the Port Authority of Tarragona

 

SETMANES DE L'AIGUA | PORT TARRAGONA | De l'11 d'abril al 5 de maig

 ACTE CENTRAL 25 I 26 D'ABRIL - INSCRIPCIONS

 

 Acte central - 25 i 26 abril. Jornades Tècniques | La Gestió de l'aigua en un escenari de crisi climàtica. L’objectiu de les Jornades tècniques és abordar amb els actors implicats la complexitat de la gestió de l’aigua des d’una visió transversal: climàtica, ambiental, social i de governança. Més enllà de la sequera actual i de les incògnites que planteja, cal avançar cap a una gestió sostenible dels recursos hídrics.

Inscripcions 25 i 26 abril

25 i 26 abril

Registra't ara
+ info

L'AIGUA DEL FUTUR DE L'11 D'ABRIL AL 5 DE MAIG.És un esdeveniment compost de diverses jornades tècniques, debats, exposicions i art al Port de Tarragona que tindrà lloc durant els dies compresos entre l'11 d'abril i el 5 de maig en diversos punts del Port de Tarragona. Amb l'objectiu d'informar-vos sobre tota la programació i que no us perdeu res, us deixem totes les activitats a continuació:

 

Pàgina oficial de les Setmanes de l'Aigua Port Tarragona- Agenda i programació - accés lliure

 

Pàgina oficial Primera edició

Més informació PROGRAMACIÓ 
+ info

 

Mitjans col·laboradors