The Port of Tarragona lays the first caisson of the Balears Wharf

The Port of Tarragona lays the first caisson of the Balears Wharf
17 Aug
2020

Three of the eleven caissons needed have already been manufactured on the “Mar del Aneto” floating dock

The first caisson has now been installed on the Balears Wharf. This was one of the most complex operations as it was the initial foundation and had to be placed without a prior reference point. Its placement was only possible following confirmation that the previous levelling operation had been completed correctly.

The complex operation for laying this first caisson was carried out in six and a half hours. It was probably the slowest of the operations, as there were no other caissons on which to support it.

These concrete foundations are placed on the ballast base material once the foundation layer and levelling gravel have been verified as correct.

Once manufactured, the caissons are moored near the Catalunya Wharf while they acquire strength and the pertinent safety measures are prepared for when they are ready to be installed.

Construction forging ahead at a good pace

Caisson production on the “Mar del Aneto” floating dock has reached cruising speed with the completion of the third caisson for the Balears Wharf. Caisson construction has surpassed the expected rate of one per week by approximately 25%.

In total 11 caissons 41.05 m long, 16.75 m wide and 21.30 m high will be built. The weight of an empty caisson is 7,288.80 tones, while it is calculated that a full one will weigh 33,440.65 tons.

The Balears Wharf construction is now in the fourth of a total of ten phases. This phase is being carried out in parallel with some of the earlier phases, such as the caisson manufacture and the laying from a barge of the rockfill material from the Vallcarca quarry.

 

Tagged under
  • Creuers a Tarragona
  • Creuers
  • Moll de Balears

Most Visited

Work with us

Work with us

Job board of the Port Authority of Tarragona
Open Data

Open Data

Here you will find public data of the public character of the organization
Contractor Profile

Contractor Profile

Here you will find public data of the public character of the organization
Communication and press

Communication and press

News of interest and current affairs of the Port Authority of Tarragona
SEA

SEA

AGRI-FOOD DELIVERY SYSTEM
Ship location

Ship location

Gisweb, ship situation program, stopovers and movements
Requests for services via ports

Requests for services via ports

Requests for services and communications for the ship, the goods and the passage
Accreditation center

Accreditation center

Administrative process involved in certifying a company/organization to access the Port
Traffic

Traffic

Goods traffic at the Port Authority of Tarragona

 

SETMANES DE L'AIGUA | PORT TARRAGONA | De l'11 d'abril al 5 de maig

 ACTE CENTRAL 25 I 26 D'ABRIL - INSCRIPCIONS

 

 Acte central - 25 i 26 abril. Jornades Tècniques | La Gestió de l'aigua en un escenari de crisi climàtica. L’objectiu de les Jornades tècniques és abordar amb els actors implicats la complexitat de la gestió de l’aigua des d’una visió transversal: climàtica, ambiental, social i de governança. Més enllà de la sequera actual i de les incògnites que planteja, cal avançar cap a una gestió sostenible dels recursos hídrics.

Inscripcions 25 i 26 abril

25 i 26 abril

Registra't ara
+ info

L'AIGUA DEL FUTUR DE L'11 D'ABRIL AL 5 DE MAIG.És un esdeveniment compost de diverses jornades tècniques, debats, exposicions i art al Port de Tarragona que tindrà lloc durant els dies compresos entre l'11 d'abril i el 5 de maig en diversos punts del Port de Tarragona. Amb l'objectiu d'informar-vos sobre tota la programació i que no us perdeu res, us deixem totes les activitats a continuació:

 

Pàgina oficial de les Setmanes de l'Aigua Port Tarragona- Agenda i programació - accés lliure

 

Pàgina oficial Primera edició

Més informació PROGRAMACIÓ 
+ info

 

Mitjans col·laboradors