The Port of Tarragona has already manufactured 50% of the caissons for the Balears Wharf

The Port of Tarragona has already manufactured 50% of the caissons for the Balears Wharf
04 Sep
2020

The floating dock “Mar del Aneto” has already manufactured 6 caissons at a rate of one per week Caisson placement is going ahead in parallel and at the same rate

Five of the eleven planned caissons have been installed so far on the Balears Wharf

 

Construction of the Port of Tarragona’s new Balears Wharf is advancing at the planned rate. This week it passed the halfway point in the manufacture and placement of the 11 planned caissons. To date, the floating dock “Mar del Aneto” has manufactured 6 caissons at a rate of one per week and is currently working on a seventh. At the same time and at the same rate of one per week, 5 caissons have been placed on the site destined for the new wharf.

Fifty people are working in shifts 24 hours a day, seven days a week on the manufacture of the caissons. In parallel, the concrete foundations are being laid in what will be the definitive position of the future Balears Wharf. This process, a highly complex task requiring great precision, is being undertaken by the port’s different technical services.

 

A complex operation

 

A total of 11 caissons will be manufactured. Each is 41.05 m long, 16.75 m wide and 21.30 m high. Empty, each caisson weighs 7,288.80 tons, while their weight when full is calculated to be 33,440.65 tones.

Extracting and placing the caissons is very complex operation. With the installation of the first caissons, the teams involved gained valuable experience and they are now able to work at an increasingly faster pace.

Once the construction of a caisson has been completed, an operation involving different port services is carried out. The tug service extracts the caisson using the moorings and ropes installed for the purpose of removing it from the floating dock. It is then left in the area of the Catalunya Wharf where it continues to acquire strength and the safety measures necessary for its subsequent installation are fitted.

 

Another service involved in this operation is that of boatmen and mooring. From their smaller, lighter vessels they support the main task of the tug in completing the extraction procedure and mooring the caisson on the Catalunya Wharf to avoid any movement. These two services are also in attendance when the caissons are placed on the new Balears Wharf site.

 

The new Balears Wharf

 

The new Balears Wharf will have a surface area of 4 hectares and some 700 linear metres of moorings. It is destined for cruise ships and is expected to come into operation in the middle of next year. It will allow several vessels to dock simultaneously and will also be able to handle the largest cruise liners. The Port of Tarragona considers the 2020 season to be over and is now working on the programme for next year. Advance reservations for 2020 are similar to those for 2019.

Most Visited

Work with us

Work with us

Job board of the Port Authority of Tarragona
Open Data

Open Data

Here you will find public data of the public character of the organization
Contractor Profile

Contractor Profile

Here you will find public data of the public character of the organization
Communication and press

Communication and press

News of interest and current affairs of the Port Authority of Tarragona
SEA

SEA

AGRI-FOOD DELIVERY SYSTEM
Ship location

Ship location

Gisweb, ship situation program, stopovers and movements
Requests for services via ports

Requests for services via ports

Requests for services and communications for the ship, the goods and the passage
Accreditation center

Accreditation center

Administrative process involved in certifying a company/organization to access the Port
Traffic

Traffic

Goods traffic at the Port Authority of Tarragona

 

SETMANES DE L'AIGUA | PORT TARRAGONA | De l'11 d'abril al 5 de maig

 ACTE CENTRAL 25 I 26 D'ABRIL - INSCRIPCIONS

 

 Acte central - 25 i 26 abril. Jornades Tècniques | La Gestió de l'aigua en un escenari de crisi climàtica. L’objectiu de les Jornades tècniques és abordar amb els actors implicats la complexitat de la gestió de l’aigua des d’una visió transversal: climàtica, ambiental, social i de governança. Més enllà de la sequera actual i de les incògnites que planteja, cal avançar cap a una gestió sostenible dels recursos hídrics.

Inscripcions 25 i 26 abril

25 i 26 abril

Registra't ara
+ info

L'AIGUA DEL FUTUR DE L'11 D'ABRIL AL 5 DE MAIG.És un esdeveniment compost de diverses jornades tècniques, debats, exposicions i art al Port de Tarragona que tindrà lloc durant els dies compresos entre l'11 d'abril i el 5 de maig en diversos punts del Port de Tarragona. Amb l'objectiu d'informar-vos sobre tota la programació i que no us perdeu res, us deixem totes les activitats a continuació:

 

Pàgina oficial de les Setmanes de l'Aigua Port Tarragona- Agenda i programació - accés lliure

 

Pàgina oficial Primera edició

Més informació PROGRAMACIÓ 
+ info

 

Mitjans col·laboradors